Building Efficiency Upgrade
Job Details:
Building Efficiency Upgrade
Contract Date: 9/21/2011
Completion Date: 4/15/2012
Location: NY
Background: KG Power Systems was Contracted to upgrade the efficiency of Grand Central Terminal's HVAC System and Sewage System.
Project Scope
HVAC Upgrade
• 33 Air Handlers
• 19 Exhaust Fans
• 4 Booster Pumps
• Installed and Wired Yaskawa Variable Frequency Drives
• Updated and Calibrated Cooling System Flow Meters
• Installed and Calibrated Steam Flow Sensors
Compressed Air System Upgrade and Installation
• Supplied and Installed a 75 HP Variable Speed Air Compressor
• Installed and Piped (4) 480 gallons Compressed Air Receivers
• Installed (1) High Efficiency Air Filter
• Piped 2,500 Feet of Compressed Air Piping
• Installed (8) Automatic Solenoid Valves for Remote Control
• Replaced and Calibrated Pressure Regulators